Overview

The authorisation process allows individuals or organisations to legally install and operate a distributed generation system, such as rooftop solar, connected to the electricity distribution network.

Authorisation Steps

1

Application Submission

  • Submit the prescribed form under the Licences and Authorisation Regulations, 2024.
  • The Commission issues a unique registration number and acknowledgement electronically.
2

Review & Technical Feasibility

  • Application processed within 3 months of acknowledgement.
  • PUC conducts a technical feasibility study within 60 days.
  • If feasible, the Commission issues a certificate to install.
3

If Issues Are Found

  • PUC notifies applicant and Commission within 25 days.
  • Applicant has 15 days to correct issues.
  • If unresolved, application is unsuccessful or placed on a priority waiting list.
4

Installation

  • Must comply with BS 7671 standards.
  • Completion required within 180 calendar days unless extended.

Commissioning

Systems up to 100 kW (Net Billing)

  • PUC inspection and safety checks within 7 working days.
  • System synchronised and meters installed upon approval.

Systems 100 kW to 500 kW (Gross Metering)

  • Grid impact evaluation and metering arrangements agreed with PUC.
  • Commission inspection within 7 working days.
  • Safety certificate issued and system synchronised.

Authorisation Granted

Once all requirements are met, the Commission issues the authorisation to operate the distributed generation system.